Preparation for the test - Air pressure /tightness /leakage/ permeability testing of new buildings

APNT Services
Title
Go to content
Building Preparation for an Air Testing
Prior to the test being undertaken, the building must be prepared to allow effective pressurisation, and representative results to be obtained. The method of preparation referred to is generally compliant with BS EN ISO 9972:2015.

To allow pressure to equalise fully around the tested enclosure, all internal doors should be fully opened and restrained. All areas of the building to be tested should be connected by openings no smaller than a single leaf doorway (say 800mm x 2000mm). Any areas of the building where this is not achievable will be recorded and noted within the test report.

Further guidelines for preparation include: ยท
  • Internal doors to riser cupboards may be closed but should not be artificially sealed.
  • Lift doors should be closed (but not artificially sealed). Any external lift shaft vents should remain open.
  • All drainage traps should be filled with water.
  • All incoming service penetrations (e.g. power, telecoms) should be permanently sealed.
  • All external doors and windows should be closed (but not artificially sealed). The exception to this will be apertures to which test equipment is connected.
  • Trickle vents, smoke vents and all passive ventilation systems should be closed and temporarily sealed.
  • Permanently open uncontrolled natural ventilation openings should be temporarily sealed.
  • Mechanical ventilation and air conditioning systems should be turned off. These systems should be temporarily sealed to prevent air leakage through the systems during the test.

For the result of the test to be representative, the external envelope should be in its final completed state. However it may be necessary to erect some temporary seals/screens to allow the test to be undertaken, (for example if a door or window has been broken, or is missing). Any such temporary seals must be robust enough to withstand the test pressure. Temporary seals employed during the test (including the method of closure of mechanical ventilation systems) must be spot checked and recorded to inclusion in the test report.

It will normally be the responsibility of the client/main contractor to prepare the building prior to the test.